Pace Digitek Wins About Rs 2,691 Crore Order From NTPC Green
NTPC Green Energy has given Pace Digitek a Letter of Award for 600 MW / 1,800 MWh of battery storage at the NTPC REL Khavda Solar Plant in Gujarat.
Key Takeaways
- Pace Digitek won a Rs 2,691.30 crore order, including GST, from NTPC Green Energy.
- The order covers two 300 MW / 900 MWh battery storage blocks at the NTPC REL Khavda Solar Plant in Gujarat.
- The scope runs from supply and installation to civil work, plus 15 years of operations and maintenance.
- The company said the project is due to be completed by September 2027.
- Pace Digitek disclosed the award to the stock exchanges on November 16, 2026.
Table of Contents 5 sections
Pace Digitek has won a Letter of Award worth Rs 2,691.30 crore, including GST, from NTPC Green Energy Limited (NGEL) for a battery energy storage system (BESS) project in Gujarat. The Bengaluru company told the stock exchanges about the award on November 16, 2026.
The order covers two blocks, Block-01 and Block-02, each rated 300 MW / 900 MWh, at the NTPC REL Khavda Solar Plant. Together they add up to 600 MW / 1,800 MWh. Both blocks sit under Cluster-01 of a 3,300 MWh BESS project. The work includes supply, system integration, installation, testing, commissioning and civil work, followed by 15 years of operations and maintenance. The project is due to be completed by September 2027.
Pace Digitek's NTPC Green order at a glance
| Detail | Value |
|---|---|
| Company | Pace Digitek Limited |
| Awarded by | NTPC Green Energy Limited (NGEL) |
| Type | Letter of Award |
| Order value | Rs 2,691.30 crore (Rs 26,913 million), including GST |
| Site | NTPC REL Khavda Solar Plant, Gujarat |
| Capacity | Two blocks of 300 MW / 900 MWh each (600 MW / 1,800 MWh in total) |
| Wider project | Cluster-01 of a 3,300 MWh BESS project |
| Maintenance | 15 years of operations and maintenance |
| Completion | By September 2027 |
| Disclosed | November 16, 2026 |
In its disclosure, the company said the order came from a domestic entity and is not a related party transaction. It added that its promoters and promoter group have no interest in NTPC Green Energy.
How Pace Digitek moved from telecom power into battery storage
Pace Digitek was incorporated in Bengaluru in 2007 and began by supplying power systems for the telecom industry. Today it calls itself an integrated telecom and energy infrastructure company, with work across manufacturing, EPC (engineering, procurement and construction), build-own-operate projects and lifecycle services. Its shares have been listed on the BSE and NSE since October 6, 2025, after an IPO priced at Rs 219 a share.
This is not its first battery storage order from NTPC. In March 2026 Pace Digitek won an NTPC order worth Rs 4,945.4 million, or about Rs 495 crore excluding GST, for a 200 MW / 400 MWh BESS at the Nabinagar Super Thermal Power Station in Bihar.
| When | What happened |
|---|---|
| 2007 | Pace Digitek is incorporated in Bengaluru |
| October 6, 2025 | Shares list on the BSE and NSE after an IPO priced at Rs 219 a share |
| March 2026 | Wins an NTPC order of about Rs 495 crore for a 200 MW / 400 MWh BESS at Nabinagar, Bihar |
| Q2 FY27 (July to September 2026) | Revenue from operations of about Rs 808 crore, up about 51.5% from a year earlier |
| November 16, 2026 | Wins the Rs 2,691.30 crore NTPC Green Energy BESS order at Khavda |
Pace Digitek's latest quarter and revenue guidance
For the July to September 2026 quarter (Q2 FY27), Pace Digitek reported consolidated revenue from operations of about Rs 808 crore, up about 51.5% from about Rs 533 crore in the same quarter a year earlier. Consolidated profit after tax rose about 43% to about Rs 97 crore. Revenue for the first half of FY27 was about Rs 1,364 crore.
With those results, the company raised its revenue guidance for FY27 to Rs 3,300 crore to Rs 3,500 crore, from Rs 3,200 crore to Rs 3,400 crore earlier.
Where Pace Digitek stands after the Khavda award
The Khavda award is worth Rs 2,691.30 crore and covers 1,800 MWh of battery storage, more than four times the 400 MWh of its Nabinagar order from NTPC in March 2026. Pace Digitek has said it expects to finish the Khavda project by September 2027 and will then maintain it for 15 years.
More news
Frequently Asked Questions
What is Pace Digitek?
What does Pace Digitek do?
What order did Pace Digitek win?
How much is Pace Digitek's NTPC Green order worth?
How large is the battery storage capacity in Pace Digitek's order?
Where will Pace Digitek carry out the project?
What work does the order cover for Pace Digitek?
When is Pace Digitek due to complete the Khavda project?
When did Pace Digitek announce the order?
Is Pace Digitek's order a related party transaction?
How did Pace Digitek perform in Q2 FY27?
How much revenue does Pace Digitek expect in FY27?
More in Business
Hindustan Zinc Approves About Rs 80,000 Crore Expansion Plan
Hindustan Zinc plans to spend about Rs 80,000 crore to raise its metal capacity to 2.0 MTPA.
PTC Industries H1 Profit Rises About 168% to Rs 62.47 Crore
PTC Industries posted a Rs 62.47 crore consolidated profit for H1 FY27, up about 168% from a year ago.
Glenmark Pharmaceuticals Launches Generic Inlyta Tablets in US
Glenmark Pharmaceuticals has launched an authorized generic of Pfizer's kidney cancer drug INLYTA in the US.