Back

Adani Energy Solutions Wins a Bihar Transmission Project

The project will carry 2,400 MW from the Pirpainti power plant and bring an annual tariff of about Rs 500 crore.

Adani Energy Solutions business news: the Adani Energy Solutions logo over an aerial photo of a power plant and switchyard at sunrise

Key Takeaways

  • Adani Energy Solutions won the Bihar project through Tariff Based Competitive Bidding.
  • The project will carry 2,400 MW from Adani Power's upcoming Pirpainti plant.
  • The company said it will bring an annual tariff of about Rs 500 crore once commissioned.
  • It adds 881 ckm of lines and 3,160 MVA of transformation capacity.
  • Vikramshila Power Transmission Ltd will run the project, due by the last quarter of 2028.
Table of Contents 6 sections
  1. Adani Energy Solutions' Bihar project at a glance
  2. The substations and lines AESL will build across Bihar
  3. AESL's recent run of transmission wins
  4. Kandarp Patel on what the Pirpainti lines will do for Bihar
  5. Where AESL's network stands after the Bihar win
  6. FAQs

Adani Energy Solutions Limited (AESL) said on November 19, 2026 that it has won a transmission project in Bihar to carry power from the upcoming 2,400 MW power plant at Pirpainti. The plant is being built by Adani Power. AESL won the project through the Tariff Based Competitive Bidding (TBCB) process.

The company said the project will bring in an annual tariff of about Rs 500 crore once it is commissioned. It will be run through a special purpose vehicle called Vikramshila Power Transmission Ltd and is due to be delivered by the last quarter of 2028.

Adani Energy Solutions' Bihar project at a glance

DetailValue
CompanyAdani Energy Solutions Limited (AESL)
Project nameEvacuation of Power from 3X800 MW STPP Pirpainti
Power to be carried2,400 MW from the Pirpainti power plant
How it was wonTariff Based Competitive Bidding (TBCB)
Annual tariffAbout Rs 500 crore once commissioned
Project companyVikramshila Power Transmission Ltd
Transmission lines881 circuit kilometres (ckm)
Transformation capacity3,160 MVA
DeliveryBy the last quarter of 2028

The substations and lines AESL will build across Bihar

The project includes four gas insulated substations at Jhanjharpur, Bethauli and Begusarai. It will have 400 kV double circuit lines linking Pirpainti with Jhanjharpur, Pirpainti with Begusarai and Begusarai with Bakhtiyarpur, plus 220 kV lines linking Jhanjharpur with Bethauli and Begusarai with Begusarai Town.

The work also covers changes to existing 220 kV and 132 kV lines at Jhanjharpur and new 400 kV line bays at the Bakhtiyarpur grid substation. The company said that besides carrying power from the Pirpainti plant, the project will strengthen the state's transmission network and improve supply reliability.

AESL's recent run of transmission wins

AESL is part of the Adani Group and works in power transmission, electricity distribution, smart metering and cooling solutions. Its distribution business serves about 13 million consumers in Mumbai and the Mundra SEZ. Before the Bihar win, AESL won transmission projects in Andhra Pradesh in July 2026 and in Maharashtra in August 2026.

WhenWhat happened
July 2026AESL wins an inter-state transmission project of about Rs 8,500 crore in Andhra Pradesh, for planned green hydrogen and green ammonia projects in the Vizag area
August 2026AESL wins a transmission project of about Rs 4,700 crore in Maharashtra, linked to pumped storage near Satara
November 19, 2026AESL says it has won the Pirpainti transmission project in Bihar

Kandarp Patel on what the Pirpainti lines will do for Bihar

"The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone. It will enhance grid reliability and resilience and help the state meet its growing power demand."

Kandarp Patel, CEO, Adani Energy Solutions

Where AESL's network stands after the Bihar win

The company said the Bihar project will add 881 ckm of transmission lines and 3,160 MVA of transformation capacity, taking its portfolio to 30,683 ckm and 146,585 MVA. AESL said its transmission capex now stands at about Rs 91,500 crore with this project. The company said the project will be delivered by the last quarter of 2028.

More news

Join Us Add as preferred source
Share

Frequently Asked Questions

What is Adani Energy Solutions?

Adani Energy Solutions Limited (AESL) is an Adani Group company that works in power transmission, electricity distribution, smart metering and cooling solutions.

What project has Adani Energy Solutions won in Bihar?

Adani Energy Solutions has won a transmission project to carry 2,400 MW of power from the upcoming Pirpainti power plant in Bihar.

How did Adani Energy Solutions win the Bihar project?

Adani Energy Solutions won the Bihar project through the Tariff Based Competitive Bidding (TBCB) process.

How much annual tariff will the Bihar project bring Adani Energy Solutions?

Adani Energy Solutions said the Bihar project will bring in an annual tariff of about Rs 500 crore once it is commissioned.

What is the name of Adani Energy Solutions' Bihar project?

The Adani Energy Solutions project is titled Evacuation of Power from 3X800 MW STPP Pirpainti.

Which company will run the Adani Energy Solutions Bihar project?

Adani Energy Solutions will carry out the Bihar project through a special purpose vehicle called Vikramshila Power Transmission Ltd.

When will Adani Energy Solutions deliver the Bihar project?

Adani Energy Solutions said the Bihar project will be delivered by the last quarter of 2028.

How many kilometres of lines will the Bihar project add for Adani Energy Solutions?

The Bihar project will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity to Adani Energy Solutions' portfolio.

How big will Adani Energy Solutions' transmission portfolio be after the Bihar project?

Adani Energy Solutions said the Bihar project takes its portfolio to 30,683 ckm of lines and 146,585 MVA of transformation capacity.

Where will Adani Energy Solutions build substations in Bihar?

Adani Energy Solutions will build four gas insulated substations at Jhanjharpur, Bethauli and Begusarai.

Who is the CEO of Adani Energy Solutions?

Kandarp Patel is the CEO of Adani Energy Solutions.

How much is Adani Energy Solutions' transmission capex now?

Adani Energy Solutions said its transmission capex stands at about Rs 91,500 crore with the Bihar project.

More in Business