Vikram Solar Q2 Profit Falls About 95% to Rs 5.93 Crore

Vikram Solar's revenue from operations slipped 2.9% to Rs 1,077 crore, and its order book rose to 8.2 GW.

Vikram Solar results: the Vikram Solar logo over rows of solar panels under a cloudy sky

Key Takeaways

  • Vikram Solar's Q2 FY27 net profit fell about 95% to Rs 5.93 crore from about Rs 128.5 crore.
  • Revenue from operations fell 2.9% to Rs 1,077 crore from Rs 1,110 crore.
  • EBITDA fell about 57% to Rs 101 crore, and the margin dropped to 9.4% from 21.2%.
  • The company added about 1.7 GW of orders, taking its order book to 8.2 GW.
  • Vikram Solar said its 9 GW cell plant will make its first cell in December 2026.
Table of Contents 7 sections
  1. Vikram Solar Q2 FY27 at a glance
  2. Vikram Solar's profit and revenue also fell from the June quarter
  3. Vikram Solar sold more through distribution and DCR modules
  4. How Vikram Solar's order book and results have moved
  5. What Vikram Solar said about its cell and battery plants
  6. Where Vikram Solar stands after its September quarter
  7. FAQs

Vikram Solar reported a consolidated net profit of Rs 5.93 crore for the July to September 2026 quarter (Q2 FY27), down about 95% from about Rs 128.5 crore in the same quarter a year earlier. Revenue from operations fell 2.9% to Rs 1,077 crore from Rs 1,110 crore.

EBITDA fell about 57% to Rs 101 crore from Rs 235 crore, and the EBITDA margin dropped to 9.4% from 21.2%. Sales volume was 591 MW, down about 25% from a year earlier. The solar module maker added about 1.7 GW of new orders in the quarter, which took its order book to 8.2 GW.

Vikram Solar Q2 FY27 at a glance

DetailValue
QuarterJuly to September 2026 (Q2 FY27), consolidated
Net profitRs 5.93 crore, down about 95% from about Rs 128.5 crore
Revenue from operationsRs 1,077 crore, down 2.9% from Rs 1,110 crore
EBITDARs 101 crore, down about 57% from Rs 235 crore
EBITDA margin9.4%, from 21.2% a year earlier
Sales volume591 MW, down about 25% from a year earlier
New orders in the quarterAbout 1.7 GW, from 0.8 GW in Q1 FY27
Order book8.2 GW at September 30, 2026

Vikram Solar's profit and revenue also fell from the June quarter

Compared with the April to June 2026 quarter (Q1 FY27), revenue from operations fell about 31% from Rs 1,563 crore, and net profit fell about 70% from about Rs 20 crore. EBITDA per watt rose about 37% from the June quarter to Rs 1.71.

For the first half of FY27, revenue from operations rose 17.7% to about Rs 2,641 crore. Net profit for the half year fell about 90% to about Rs 25.7 crore from Rs 261.85 crore a year earlier.

Vikram Solar sold more through distribution and DCR modules

Distribution made up 44% of Vikram Solar's Q2 FY27 sales volume, up from 14% in the June quarter. Modules sold under the Domestic Content Requirement (DCR) rules made up 22% of volume, up from 7.5%. The company has 15.5 GW of module manufacturing capacity.

How Vikram Solar's order book and results have moved

WhenWhat happened
July to September 2025 (Q2 FY26)Revenue from operations of about Rs 1,110 crore, net profit of about Rs 128.5 crore, order book of 11.15 GW
April to June 2026 (Q1 FY27)Revenue from operations of Rs 1,563 crore, net profit of about Rs 20 crore, order book of 7.9 GW
July to September 2026 (Q2 FY27)Revenue from operations of Rs 1,077 crore, net profit of Rs 5.93 crore, order book of 8.2 GW

What Vikram Solar said about its cell and battery plants

Vikram Solar said its 9 GW solar cell plant at Gangaikondan in Tamil Nadu is on track to make its first cell in December 2026, and its investor presentation puts the start of commercial production in March 2027. The company said it plans 9 GW of ingot and wafer capacity at the same site by FY29.

The company also said its wholly owned unit VSL PowerHive is building a 7.5 GWh battery energy storage (BESS) plant at Oragadam near Chennai, which can be scaled to 15 GWh. Vikram Solar said it expects the plant to start commercial operations in April 2027.

Where Vikram Solar stands after its September quarter

Vikram Solar's Q2 FY27 net profit fell about 95% to Rs 5.93 crore as revenue from operations slipped 2.9% to Rs 1,077 crore and the EBITDA margin fell to 9.4%. Its order book rose to 8.2 GW from 7.9 GW at the end of June. The company said its first cells from the Gangaikondan plant are due in December 2026.

More news

Join Us Add as preferred source
Share

Frequently Asked Questions

What is Vikram Solar?

Vikram Solar is an Indian solar module maker with 15.5 GW of module manufacturing capacity.

How much profit did Vikram Solar make in Q2 FY27?

Vikram Solar reported a consolidated net profit of Rs 5.93 crore for the July to September 2026 quarter.

How much did Vikram Solar's Q2 profit fall?

Vikram Solar's Q2 FY27 net profit fell about 95% from about Rs 128.5 crore in the same quarter a year earlier.

What was Vikram Solar's revenue in Q2 FY27?

Vikram Solar's revenue from operations was Rs 1,077 crore in Q2 FY27, down 2.9% from Rs 1,110 crore a year earlier.

What was Vikram Solar's EBITDA margin in Q2 FY27?

Vikram Solar's EBITDA margin was 9.4% in Q2 FY27, compared with 21.2% a year earlier, on EBITDA of Rs 101 crore.

How did Vikram Solar's Q2 compare with the June quarter?

Vikram Solar's revenue from operations fell about 31% from Rs 1,563 crore and its net profit fell about 70% from about Rs 20 crore in the June quarter.

How big is Vikram Solar's order book?

Vikram Solar's order book stood at 8.2 GW at September 30, 2026, up from 7.9 GW at the end of June.

How many new orders did Vikram Solar add in Q2 FY27?

Vikram Solar added about 1.7 GW of new orders in Q2 FY27, compared with 0.8 GW in Q1 FY27.

How did Vikram Solar do in the first half of FY27?

Vikram Solar's first-half revenue from operations rose 17.7% to about Rs 2,641 crore, while its net profit fell about 90% to about Rs 25.7 crore.

What share of Vikram Solar's volume came from distribution?

Distribution made up 44% of Vikram Solar's Q2 FY27 sales volume, up from 14% in the June quarter.

When will Vikram Solar's cell plant start?

Vikram Solar said its 9 GW cell plant at Gangaikondan in Tamil Nadu will make its first cell in December 2026, and its presentation puts commercial production in March 2027.