CtrlS Signs MoU for Rs 10,000 Crore AI Data Centre in Bihar
CtrlS Datacenters signed an MoU with the Bihar government for a 150 MW AI-ready data centre, a month after its letter of intent.
Key Takeaways
- CtrlS signed an MoU with the Bihar government on November 20, 2026.
- The planned investment is Rs 10,000 crore for a 150 MW AI-ready data centre.
- CtrlS said the site is a 100-acre plot, preferably in or around Patna.
- The company aims for commercial operations by 2029-30 and 400 direct jobs.
- The MoU follows a letter of intent CtrlS signed in October 2026.
Table of Contents 6 sections
CtrlS Datacenters signed a memorandum of understanding (MoU) with the Bihar government on November 20, 2026, to invest Rs 10,000 crore in a 150 MW hyperscale AI facility in the state. The company said the MoU follows a letter of intent it signed with the state government last month.
CtrlS said the AI-ready data centre aims to start commercial operations by 2029-30 and will create 400 direct jobs, 100 of them on-site and 300 through hosted customers. The company said the facility will come up on a 100-acre plot close to a 220/400 kV substation, preferably in or around Patna.
CtrlS Bihar data centre MoU at a glance
| Detail | Value |
|---|---|
| Company | CtrlS Datacenters Ltd |
| Agreement | MoU with the Bihar government |
| Signed | November 20, 2026, in Patna |
| Planned investment | Rs 10,000 crore |
| Capacity | 150 MW |
| Site | 100-acre plot near a 220/400 kV substation, preferably in or around Patna |
| Commercial operations target | 2029-30 |
| Direct jobs | 400 (100 on-site, 300 through hosted customers) |
CtrlS moves from a letter of intent to an MoU in Bihar
A CtrlS delegation led by Chief Operating Officer Sudarshan Malpani met officials of Bihar's Department of Industries in Patna and signed the MoU in the presence of Chief Minister Samrat Choudhary, the company said. The MoU builds on the letter of intent CtrlS signed for the same Rs 10,000 crore, 150 MW project in October 2026. Reports of that letter of intent named Bodh Gaya as the location, while the company's MoU announcement says the site is preferably in or around Patna.
CtrlS already runs a Rs 400 crore AI and cloud-ready data centre in the Patliputra Industrial Area of Patna, which was inaugurated in October 2026. The company said that facility offers an IT load of 12 MW, with room to expand as demand grows.
| When | What happened |
|---|---|
| 2007 | CtrlS Datacenters began operations |
| October 2026 | Opened a Rs 400 crore, 12 MW data centre in Patna and signed a letter of intent for a Rs 10,000 crore, 150 MW AI facility in Bihar |
| November 20, 2026 | Signed an MoU with the Bihar government for the Rs 10,000 crore, 150 MW facility |
Sridhar Pinnapureddy on investment and jobs in Bihar
"We are committed to strengthening Bihar’s digital infrastructure and building a robust IT ecosystem through our future-ready data centres, designed to serve the evolving needs of hyperscalers, enterprises, and startups. Through the MoU, we will bring significant investments into Bihar while creating new employment opportunities and contributing to the region’s economic growth."
CtrlS's data centre network beyond Bihar
CtrlS said it operates 19 data centres across nine markets in India and plans to build over 4.4 GW of data centre capacity by 2030. The company has also said it plans to explore markets in Southeast Asia and the Middle East, with Thailand as its first international market.
Where CtrlS stands in Bihar after the MoU
With the MoU, CtrlS has a signed agreement with the Bihar government for a Rs 10,000 crore, 150 MW AI-ready data centre, in addition to its 12 MW facility in Patna. The company said the new facility aims to begin commercial operations by 2029-30 and create 400 direct jobs.
More news
Frequently Asked Questions
What is the CtrlS Bihar data centre?
How much will CtrlS invest in Bihar?
When did CtrlS sign the MoU with Bihar?
What is the capacity of the planned CtrlS data centre in Bihar?
Where will the CtrlS Bihar data centre be built?
How many jobs will the CtrlS Bihar data centre create?
When will the CtrlS Bihar data centre start operations?
How is the MoU different from the earlier letter of intent?
Who signed the MoU for CtrlS?
Does CtrlS already have a data centre in Bihar?
How many data centres does CtrlS operate?
How much capacity does CtrlS plan to build by 2030?
More in Investments
Chubu Electric Completes Rs 1,350 Crore Continuum Investment
Chubu Electric Power has completed its Rs 1,350 crore investment in Continuum Green Energy.
Bank of America Arm Leases 10.1 Lakh Sq Ft Office in Hyderabad
Bank of America's BA Continuum India has leased about 10.1 lakh sq ft at Mindspace Cyberabad.
Motilal Oswal Alternates Launches a Grade A Office Fund
Motilal Oswal Alternates has launched its first fund dedicated to commercial real estate.